Building work

Friday 18th October

The builders have now completed Phase 2 of the building work, with the foundations, lower wall and slabs laid.

Over the next few weeks the windows are being custom made ready for fitting. During this time the remaining fencing will be removed.

Wednesday 16th October

The site is now all clear and work has started on putting in the new foundations of the extension.

Luckily even though the weather has been terrible the builders have still managed to keep to schedule.

Monday 14th October

Today the mini digger has arrived and the demolition starts.

It is very sad to see the building slowly being knocked down.

Friday 11th October

With the grounds and room all secure, work has started in the removal of the roof, this means carefully removing each piece of glass and the safe disposal of all the fixtures and fittings.

Thursday 10th October

This month see major building work taking place at the Nursery. The old conservatory part of the Butterfly room is being demolished and rebuilt. The original building had a tendency to leak if it rained.

The work will take place over several weeks and by Christmas we will have a brand new extension, completely re-decorated and leak free.

The children have been very excited to see ‘Bob’ the builder’s wandering around and I am sure they will keep you all updated with the progress.

Posts will be updated regularly for parents.